Bit more background from Southern Link Upgrade project:
The Southern Link Upgrade project has a number of priorities when it comes to works under the Burnley Viaduct, namely yourselves, Bicycle Victoria, Parks Victoria and CityLink. Priorities for works to be completed in this section have been developed as follows:
Complete works defined as ‘Category A’, which consist of the two southern beams and defined crossheads;
Complete works defined as ‘Category B’ which are required to be cleared prior to the Yarra Trail being reopened;
Complete ‘Category B’ works between piers 12 and 13 which will allow the Burnley Climbing Walls 2 and 3 to reopen; and
Complete all remaining works to hand back the area to Parks Victoria, including reopening Burnley Climbing Wall 1.
Once works commence and we understand our productivities a little better we will be in a position to provide some anticipated dates for completion of the works defined above.